APPSC Group-I Prelims 2022 — Paper-I (General Studies) · Q 82
Polavaram Project is a
- (a) National Project.
- (b) State Project.
- (c) Inter-State Project.
- (d) Joint Venture Project.
Official APPSC answer: (a)
Solution: The answer is (A): Polavaram is a National Project because Section 90 of the Andhra Pradesh Reorganisation Act, 2014 made the Union Government responsible for executing it and for bearing 100% of the cost of its irrigation component. Option-by-option analysis • ✅ (A) National Project. — The Polavaram Irrigation Project on the Godavari was taken over by the Union Government under Section 90 of the Andhra Pradesh Reorganisation Act, 2014. From 1 April 2014, the Centre bears 100% of the cost of the irrigation component. The project is officially treated and funded as a National Project, and a Polavaram Project Authority was set up in 2014 to monitor it. • ❌ (B) State Project. — The Andhra Pradesh government works as the executing agency on the ground, but that is only the implementing arrangement. The money comes from the Union, and the responsibility to execute the project was placed on…
APPSC Group-I Prelims 2022 — Paper-II (General Aptitude) · Q 91
Pick out the correct matches from the following statements regarding externally-aided projects in Andhra Pradesh :
I. Andhra Pradesh Integrated Irrigation and Agriculture Transformation Project is aided by the World Bank.
II. Andhra Pradesh Community Managed Natural Farming (APCNF) is aided by Japan International Co-operation Agency (JICA).
III. Andhra Pradesh Irrigation and Livelihood Improvement Project Phase-3 is aided by KfW – German Bank.
- (a) Only I and II are correct
- (b) Only I and III are correct
- (c) I, II and III are correct
- (d) Only I is correct
Official APPSC answer: (d)
Solution: The answer is (D): only statement I is correct, because APIIATP is genuinely World Bank-aided, while APCNF is a state-supported (RySS) programme, not JICA-aided, and APILIP has been JICA-assisted, not KfW-assisted. Statement-by-statement analysis • ✅ I — The Andhra Pradesh Integrated Irrigation and Agriculture Transformation Project (APIIATP) is a World Bank-financed project, with the loan agreement signed in 2021. Its aim is to modernise canal and tank irrigation and to link farmers to markets, so the World Bank tag fits perfectly. Notice that every option (A)–(D) includes statement I; the examiners made it the guaranteed base and built the choice on II and III. • ❌ II — APCNF (Andhra Pradesh Community Managed Natural Farming) is not a JICA-aided project. It is implemented by Rythu Sadhikara Samstha (RySS), a non-profit set up by the Government of Andhra Pradesh, and is supported mai…
APPSC Group-I Prelims 2018 — Paper-I (General Studies) · Q 87
After bifurcation, according to the suggestions of NITI Aayog, who has to take the construction responsibility of the Polavaram Project?
- (a) State Government
- (b) Central Government
- (c) Central Water Commission
- (d) Polavaram Project Authority
Official APPSC answer: (a)
Solution: The answer is (A): NITI Aayog recommended that the Andhra Pradesh State Government execute the Polavaram Project, with the Centre declaring it a national project and reimbursing the approved irrigation cost. Option-by-option analysis • ✅ (A) State Government — NITI Aayog suggested that the Andhra Pradesh State Government should take the construction and execution responsibility of Polavaram. The Centre treats Polavaram as a national project under Section 90 of the AP Reorganisation Act, 2014, and reimburses the approved cost of the irrigation component. So the builder is the State, while the payer is the Centre. • ❌ (B) Central Government — The Central Government declares the project national, releases and reimburses funds, and monitors it through agencies. But it does not itself take up the civil construction of Polavaram. After bifurcation, NITI Aayog's suggestion left the actual co…
APPSC Group-I Screening Test 2016 (Notification 36/2016) — General Studies & Mental Ability · Q 15
With regard to funding of the Polavaram Project, the Centre would provide
- (a) 100% of the cost of the irrigation component for the period starting from 01/04/2014 to the extent of the cost as on that date
- (b) 100% of the cost of the irrigation component as incurred
- (c) 100% of the cost of the irrigation component as per value decided by the Centre
- (d) 100% of the cost of the full project for the period starting from 01/04/2014 to the extent of the cost as on that date
Official APPSC answer: (a)
Solution: The answer is (A): the Centre would provide 100% of the cost of the irrigation component only, for the period starting from 01/04/2014, limited to the cost as on that date. Option-by-option analysis • ✅ (A) — It matches the Union decision: the Centre bears 100% of the cost of the irrigation component of Polavaram for the period starting from 01/04/2014, and the liability is limited to the cost as on that date. It does not cover the full project or expenditure before that date. • ❌ (B) — The phrase as incurred would make the Central share open-ended. It could include irrigation expenditure before 01/04/2014 and later cost revisions. The actual commitment has a cut-off date and a cost limit, so this option is too broad. • ❌ (C) — It makes the amount depend on a value decided by the Centre in a discretionary way. The keyed formula is tied to the cost of the irrigation component as on 01/…