APPSC Group-I Prelims 2024 — Paper-II (General Aptitude) · Q 17
Neelima places an order for 'p' number of sweets from Agarwal Sweet Shop that produces 'q' number of sweets every day. r% of the total number of sweets produced in a day fail quality check and are discarded. What will be the number of days in which the order will be completed?
- (a) $\dfrac{100r}{q(100-p)}$
- (b) $\dfrac{p}{100q(1-r)}$
- (c) $\dfrac{100qr}{p}$
- (d) $\dfrac{100p}{(100-r)q}$
Official APPSC answer: (d)
Solution: The answer is (D) $\dfrac{100p}{(100-r)q}$. Only the passing sweets are useful, so days = p ÷ [q(100-r)/100] = 100p/[(100-r)q].
APPSC Group-I Prelims 2024 — Paper-II (General Aptitude) · Q 37
A, B and C are hired for a painting job. Working together, A and B can do a job in 12 days, B and C can do the same job in 8 days, while A and C can do it in 16 days. Then how long will it take, if all of them work together to complete the job?
- (a) $7\frac{5}{13}$ days
- (b) $7\frac{7}{13}$ days
- (c) $3\frac{7}{12}$ days
- (d) $3\frac{7}{13}$ days
Official APPSC answer: (a)
Solution: The answer is (A) $7\frac{5}{13}$ days, because the combined one-day rate is $\frac{13}{96}$ and its reciprocal is $\frac{96}{13}$ days.
APPSC Group-I Prelims 2022 — Paper-II (General Aptitude) · Q 51
The ratio of jobs done by 30 girls to the job done by 25 boys, in the same time period is 5 : 6. If 9 girls and 10 boys can finish a job in 40/13 days, then how many girls are required to complete the job in 6 days ?
- (a) 13
- (b) 10
- (c) 12
- (d) 15
Official APPSC answer: (c)
Solution: The answer is (C) 12 — the job is 72 girl-days of work, and 72 ÷ 6 = 12 girls.
APPSC Group-I Prelims 2018 — Paper-II (General Aptitude) · Q 22
A man can do a piece of work in 5 days, but with the help of his son, he can do it in 3 days. In what time can the son do it alone?
- (a) 7½ days
- (b) 8 days
- (c) 15 days
- (d) 6 days
Official APPSC answer: (a)
Solution: The answer is (A) 7½ days, because the son's one-day work is $\frac{1}{3}-\frac{1}{5}=\frac{2}{15}$, so alone he takes $\frac{1}{2/15}=\frac{15}{2}=7\frac{1}{2}$ days.
APPSC Group-I Prelims 2018 — Paper-II (General Aptitude) · Q 48
A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 more days. In how many days will A and B together finish the work?
- (a) 8
- (b) 6
- (c) 10
- (d) 12
Official APPSC answer: (a)
Solution: The answer is (A) 8 — A does $\frac14$ in 5 days, so B does the remaining $\frac34$ in 10 days at $\frac{3}{40}$ per day; together they do $\frac{1}{20}+\frac{3}{40}=\frac18$ per day, giving 8 days.